01
Roof
- Trade
- Roofer
- Timing
- Always first. 1 to 3 days on site.
Roof flashing tucks behind siding. If siding goes first, roofers later cut into the new siding. Destroyed work, voided warranties.
Sheet · Order of work
6 phases · Top-down
No contractor owns the cross-trade sequence. Doing siding before the roof means tearing into new siding for flashing later. This is the canonical order that protects what you pay for.
01
Roof flashing tucks behind siding. If siding goes first, roofers later cut into the new siding. Destroyed work, voided warranties.
02
Openings before siding so the moisture barrier and capping integrate. After siding means visible trim issues and paying twice for wrap labour.
03
Seal the envelope only after the roof and openings are set. Done early, everything else cuts into your new wall.
04
Paint and trim after the envelope is closed. Earlier and it gets damaged or over-painted by later trades.
05
Drainage failures end up being foundation problems. Tie this to the roof phase so the crew that owns the water path also owns the path off the house.
06
Roofing and siding crews, ladders, dumpsters destroy new plantings and hardscape. Holding this until the end is non-negotiable.
Annotations
Patterns to refuse
Note
Refuse. The roofer will tear into your new siding for flashing.
Note
Refuse. The next trade will damage or over-paint your fresh work.
Note
Hold to the end. Crews and dumpsters will crush new plantings and hardscape.